Victoria Pass Repair Reaches Major Milestone as Third-Lane Design Is Released

Work to restore the Great Western Highway at Victoria Pass has reached a major construction milestone, with piling completed for the new two-lane bridge structure at Mitchell’s Causeway and final designs released for an additional eastbound climbing lane.

Construction crews have completed 54 major piles, each extending up to 20 metres into bedrock, which will support the new roadway above the existing causeway.

The piling work followed the installation of 53 micro piles, which were needed to stabilise the site and allow large piling rigs weighing 76 tonnes and 40 tonnes to operate safely on the causeway.

Road Deck Construction to Begin

With the major piles now in place, the next phase will involve construction of the reinforced concrete road deck.

The new structure will sit above and operate independently of the historic Mitchell’s Causeway, while the existing convict-era sandstone structure is stabilised and retained.

Mitchell’s Causeway opened to traffic in 1832 and supports around 150 metres of the Great Western Highway as it descends between Mount Victoria and Little Hartley.

Additional Eastbound Climbing Lane

Final designs have also been released for a new eastbound climbing lane alongside the existing roadway.

The additional lane will be supported by 14 piles and 14 columns, which will carry a separate road deck.

Over the next six weeks, crews are expected to begin construction of a five-metre-high retaining wall needed to support the piling rig that will install the foundations for the climbing lane.

Once the full project is complete, motorists travelling uphill from Little Hartley to Mount Victoria will have two lanes for the entire 2.7-kilometre length of Victoria Pass.

The additional lane is intended to provide more opportunities for motorists to overtake slower heavy vehicles and caravans on the steep ascent.

Two-Lane Reopening Targeted for Q2 2027

Transport for NSW says the Great Western Highway at Mitchell’s Causeway remains on track to reopen to two-way traffic in the second quarter of 2027, subject to site conditions, testing and construction progress.

The final completion timetable for the additional climbing lane has not yet been fixed and will depend on progress with the new piling works.

The highway has been fully closed at Victoria Pass since March 2026, after serious cracking and movement were detected in the road structure.

Investigations found that while the underlying bedrock remained stable, the roughly 200-year-old fill material inside the causeway had deteriorated and developed voids, making the road unsafe.

$200 Million Jointly Funded Project

The Great Western Highway – Mitchell’s Causeway Reconstruction has a total budget of $200 million, jointly funded by the Australian and NSW governments.

The Commonwealth has committed $100 million, matching $100 million from the NSW Government.

Major construction began in July 2026 under an alliance contract with Seymour Whyte.

More than 400 workers have been inducted onto the project, with around 70 people working on site each day.

The NSW Government has separately committed an additional $50 million to strengthen and improve detour routes across the Blue Mountains and Central West while Victoria Pass remains closed.

Transport for NSW is continuing to publish weekly construction updates and worksite images as the project moves into road deck construction and the next stage of the climbing lane works.