Proposed Queensland–NSW Gas Pipeline Opens for Public Consultation

A proposed gas pipeline linking Queensland and New South Wales has moved into public consultation after the NSW section of the project was declared Critical State Significant Infrastructure.

The Bulloo Interlink Pipeline, being developed by APA Group, would create a direct connection between the South West Queensland Pipeline and the Moomba-to-Sydney pipeline system, allowing gas from northern production areas to move more directly into southern markets.

The NSW Government says the project could increase gas transport capacity into the state by up to 38 petajoules a year, while the Environmental Impact Statement for the NSW section is being placed on public exhibition.

105-Kilometre NSW Section Under Assessment

The section currently being assessed in NSW extends for about 105 kilometres from the Queensland border to existing pipeline infrastructure near Tibooburra in the Far West.

The NSW Government estimates that section of the project at around $275 million and says it could support up to 400 construction jobs if approved.

APA’s broader project is considerably larger. The company describes the full Bulloo Interlink as an approximately 340-kilometre underground high-pressure pipeline running across Queensland and NSW, with a maximum design capacity of around 800 terajoules a day.

The government’s current NSW assessment refers to up to 700TJ a day of additional gas flows between Queensland and NSW, equivalent to as much as 38PJ annually.

CSSI Status Does Not Mean Project Is Approved

Declaring the project Critical State Significant Infrastructure gives it a dedicated assessment pathway under NSW planning laws, but does not amount to final project approval.

The proposal must still undergo environmental assessment, consideration of public submissions and a formal planning determination.

APA’s NSW application is also subject to Commonwealth environmental requirements under the Environment Protection and Biodiversity Conservation Act 1999.

The company says its Environmental Impact Statement examines environmental and social impacts, project design, stakeholder feedback and measures intended to avoid or mitigate potential impacts.

Public Submissions Open Until 16 December

The NSW Environmental Impact Statement is being exhibited from 18 November, with submissions open until 16 December 2026.

Residents, landholders, organisations and other interested parties can review the proposal and lodge submissions through the NSW Planning Portal.

Once the exhibition period closes, APA will be required to respond to issues raised before the Department of Planning, Housing and Infrastructure completes its assessment.

AEMO Warns of Gas Supply Risks From 2029

The project is being considered against a backdrop of declining gas production in southern Australia.

The Australian Energy Market Operator’s 2026 Gas Statement of Opportunities forecasts a risk of gas shortfalls during extreme peak-demand conditions in southern Australia from 2029, with additional supply expected to be needed in most scenarios from 2030.

AEMO says new pipeline, storage and supply projects could help address future shortages, but also notes that the scale of the risk depends on factors including weather, gas demand, renewable energy deployment, electricity storage and the availability of gas-powered generation.

Its modelling does not amount to an endorsement of any individual gas project.

APA Has Already Made Final Investment Decision

APA announced in October that it had reached a final investment decision on the broader Bulloo Interlink project.

The company committed approximately $700 million for construction and commissioning, in addition to a previously announced $220 million for early works including engineering, procurement and approvals.

Construction is expected to begin in early 2027, subject to the necessary approvals, with APA targeting commercial operation in winter 2029.

The project forms part of APA’s wider East Coast Gas Grid expansion program, which is intended to increase north-to-south gas transport capacity.

Gas Remains Part of NSW Energy Transition Debate

The NSW Government argues that additional gas transport capacity could support industrial users and provide flexible generation during periods when electricity demand is high or renewable output is low.

The proposal also sits within the state’s broader gas policy, which includes potential local supply from Narrabri and further exploration in the Far West.

However, the Bulloo Interlink remains subject to environmental assessment and final planning approval in NSW.

The public exhibition period therefore represents the next major step in determining whether the NSW section of the pipeline proceeds.